Growing With Faith Project

Project Timeline

May 22, 2016              Church Conference approved project

August 1, 2016            Approved for Letter of Credit

August 31 , 2016         Purchased property

September 18, 2016    Kicked off Capital Campaign

October 23, 2016        Pledge Sunday

January 17, 2017        House demolished

February 5, 2017        Used new Audio-Visual System in Worship

March 11, 2017          Garage demolition begins

January 2018             New Shed was built

March 2018               General Contractor selected

May 20, 2018             Groundbreaking Ceremony

July 31, 2018             Parking Lot completed (18 spaces)

October 7, 2018         Celebration of the Project

 

Link to Project Brochure

Link to Photo Album or Slideshow

Project Goals

Grow in our outreach to the communities we serve

Provide a place and parking area for community events and programs

Provide easy access for those unable to attend worship on Sunday mornings

Update the Audio-Visual System throughout our church

Increase our off-street parking

 

Project Finances (as of 10/31/2018)

Initial Estimate                  $171,600

Total Cost                         $216,113

LOC Balance                       $83,572

Pledges                            $116,278

Fundraising                          $9,872

Gifts                                 $100,952